Gurugram: Shri Sheetla Mata Devi Medical College and Hospital to run on PPP mode

323

The under-construction Shree Sheetla Mata Devi Medical School and Hospital at Kherki Majra, Sector 102A, will function on a Public-Personal Partnership (PPP) mannequin, and its mode of operation has been handed to the directorate of medical schooling and analysis (DMER), district administration officers mentioned on Wednesday.

In keeping with new timeline, the challenge is predicted to finish in March 2026.

Throughout a high-level digital assembly on Monday, chaired by Haryana chief secretary Anurag Rastogi, the proposal to ask non-public companions for the hospitalwas mentioned with officers from Gurugram Metropolitan Improvement Authority (GMDA).

“It’s believed that the state authorities might quickly problem a request for proposal (RFP) doc to ask non-public companions. DMER will promote for this quickly,” a senior GMDA official mentioned, requesting anonymity.

To make certain, beneath the PPP mannequin, earlier service-delivery situations resembling providing a portion of beds at subsidised charges can be finalised within the RFP earlier than the hospital turns into operational.

The medical faculty and hospital developed by the GMDA is predicted to turn out to be operational by March 2026 and it’ll enrol round 150 MBBS college students yearly, together with a capability of 883 beds for sufferers.

“The work valued at 403.50 crore is accomplished out of the overall challenge price of 593.42 crore, “ mentioned Neha Sharma, spokesperson of GMDA, including that the development is 70% performed.

In keeping with officers, structural work of the hospital’s predominant block, instructing hospital & trauma centre is accomplished. “Ending works resembling plastering, flooring, tiling, and structural glazing are in progress. Electrical and HVAC works are at a complicated stage. Ducting, AHU set up, and firefighting techniques are 85–90% full, together with their inside water provide and electrical provide,” the senior official added.

”The hospital may have three hostels and residential services for round 730 occupants. These works are full, with solely few parts {of electrical}, ducting, mechanical and firefighting installations pending,” one other senior GMDA official mentioned.

The development of the hospital began in April 2022 and it was anticipated to finish by July 2024, nonetheless, it was delayed to December 2025.In keeping with new timeline, the challenge is predicted to finish in March 2026.